Deep Foundation Pit Support and Earthwork Excavation Technology
Time:2020-03-19
Deep foundation pit support is a core technical link in high-rise building and underground engineering construction, which directly determines the safety of the construction process and the stability of surrounding buildings and underground pipelines. With the rapid development of urbanization, more and more buildings are developing towards high-rise and underground space, making the construction of deep foundation pits more and more complex, and the requirements for support technology are also increasing.
There are various types of deep foundation pit support, and the selection needs to be based on the depth of the foundation pit, soil quality, surrounding environment, construction period and cost. Sheet pile support is a common temporary support method, which is composed of steel sheet piles or precast concrete sheet piles. It has the advantages of fast construction speed, reusable use and low cost, and is suitable for shallow foundation pits with a depth of less than 5 meters and relatively stable soil quality. However, its water-stop effect is poor, so it is necessary to match the water-stop curtain when used in areas with high groundwater level.
Soldier pile and lagging support is composed of bored cast-in-place piles and shotcrete lagging. It has high rigidity and small deformation, and is suitable for foundation pits with a depth of 5-15 meters and high requirements for surrounding environmental protection. It is often used in urban central areas where there are many surrounding buildings and pipelines. Diaphragm wall support is an integrated support method of water stop and soil retention. It is formed by on-site pouring of reinforced concrete, with extremely high rigidity and excellent water-stop performance. It is suitable for ultra-deep foundation pits with a depth of more than 15 meters, soft soil foundations and foundation pits adjacent to important buildings or subway lines, but its construction cost is high and the construction period is long.
Soil nailing wall support is to insert soil nails into the soil layer, and then spray concrete surface layer to form a composite soil mass, which is often used with prestressed anchor rods. It has the advantages of low cost, simple construction and fast progress, and is suitable for foundation pits with a depth of 3-10 meters and stable soil quality. However, it is not suitable for soft soil, quicksand and other bad soil layers. In the process of earthwork excavation, the principle of "layered excavation, support first and then excavation, no over-excavation, and timely support" must be followed. For soft soil foundation pits, the excavation depth of each layer should not exceed 2 meters, and the support installation should be completed within 48 hours after excavation to avoid foundation pit deformation.